Trenching of the mainline began today on number fourteen. About 2,000 feet of pipe was installed as well as several valves. In advance of the digging all utilities are being located as well as portions of the existing irrigation system. The trencher encountered two drain lines which will be repaired prior to backfilling the trench.
With the help of the Nutt Team, several valves on the existing system have been located. This will help to isolate smaller sections of the system while work is being performed and reduce the risk of losing hitting the system, losing water and the turf drying out.
Remember that in order to complete this project prior to the fall overseeding process, equipment must continue to run while golf play is in the area. Everyone is doing their best to minimize disruption and we apologize for any inconvenience that is caused as we work to complete this project. Thank you for your patience and understanding.